Lukoil Begins Industrial Development of the Komandirshorskaya Group of Fields in the Nenets Autonomous District
Lukoil has implemented the first stage of a large investment project in the Nenets Autonomous District of Russia: after constructing and commissioning the Komandirshor oil preparation unit (OPU) with a capacity of over 800,000 tonnes of oil a year, the company began industrial development of the Komandirshorskaya group of fields, Interfax reported on September 10, 2026. The fields lie in the Layskiy Bar of the Timan-Pechora oil and gas province, and the infrastructure built under the project is expected to enable the development of nearby oil fields as well.
The first stage of a large investment project
The move to industrial development follows the completion of the project's first stage. Its central facility is the Komandirshor OPU: the unit was constructed and commissioned with a capacity of over 800,000 tonnes of oil a year, and its start-up is what allowed Lukoil to begin industrial development of the Komandirshorskaya group of fields. Construction of the OPU began in December 2023, and the commissioning of the unit completed the construction phase of the first stage.
The source describes the start of industrial development as the result of a large investment project rather than of a single construction contract: the OPU is the processing core around which the surface infrastructure of the fields was built, and the capacity of the unit sets the oil preparation throughput available to the group of fields at the current stage of the project.

Associated gas with a high hydrogen sulfide content
The Komandirshorskaya project includes a system for the preparation of associated petroleum gas with a high hydrogen sulfide (H2S) content. According to the source, this system uses technologies developed and patented in Russia. The reliance on domestically patented solutions defines the technological core of the gas preparation system and distinguishes the project from developments built around imported gas-treatment technologies.
Preparation of associated gas is a necessary part of the oil treatment chain at the fields: the gas produced together with oil has to be processed before it can be used or transported, and the high hydrogen sulfide content makes this task technically demanding. The gas preparation system therefore stands alongside the OPU as one of the two processing pillars of the first stage of the project.
Infrastructure: shift settlement, roads, power and multi-well pads
Alongside the OPU, the project delivered a full set of surface facilities required for field operations. The source lists the following objects built under the project:
- a shift settlement with residential and administrative and household buildings;
- a road network;
- external energy supply;
- an oil and gas gathering system;
- multi-well pads.
The created infrastructure is not limited to the fields of the Komandirshorskaya group: according to the source, it will also allow nearby oil fields to be developed. In other words, the settlement, the roads, the power supply and the gathering system form a base that can serve future development projects in the same area of the Timan-Pechora province.
Subsoil rights: the 2014 auction and C1 reserves
The history of the project goes back to 2014, when an auction awarded the subsoil rights for the fields of the group to Lukoil-Komi, a subsidiary of Lukoil. The category C1 reserves of the three fields named by the source are as follows:
- North Komandirshorskoye — 1.033 million tonnes;
- West Komandishorskoye — 2.113 million tonnes;
- Komandishorskoye — 1.276 million tonnes.
Location of the fields
The Komandirshorskaya group of fields is located in the Layskiy Bar of the Timan-Pechora oil and gas province, within the Nenets Autonomous District: the administrative and the geological coordinates of the project are set by exactly these two references, the district and the bar of the province.
The project timeline in three dates
- 2014 — the auction awards the subsoil rights for the North Komandirshorskoye, West Komandishorskoye and Komandishorskoye fields to Lukoil-Komi;
- December 2023 — construction of the Komandirshor OPU begins;
- September 10, 2026 — after the commissioning of the OPU, Lukoil begins industrial development of the Komandirshorskaya group of fields.
These three dates frame the project from the acquisition of the subsoil rights to the start of industrial development. Between the auction and the commissioning of the OPU, the project passed through the design and construction phases that produced the shift settlement, the road network, the external energy supply, the oil and gas gathering system and the multi-well pads described above.
Leave a comment